IMC Grupo

A Comprehensive Guide On Removing Formwork From Concrete

Removing concrete formwork can also be called striking off or stripping of formwork. This is carried out only after the concrete has cured and hardened. Although, when the formwork obstructs further construction work and/or needs to be reused in another place, engineers will want to remove the formwork earlier than the typical stipulated time.

Before  stripping of formwork from concrete structures, one must keep in mind that it shouldn’t result in:

  1. The collapse of the concrete structure under self-weight or design load.
  2. Long-term or short-term deflection of the structure.
  3. Physical damage to the concrete structure.

Early removal of concrete formwork can also result in freeze-thaw damage or cracking of the concrete due to thermal contraction. To avoid these problems, once formwork is struck off, concrete structures are insulated.

Concrete Formwork must be removed only when the concrete structure can withstand the calculated design load or at least has gained strength that is twice the stress subjected to it upon removal of formwork.

Factors Affecting The Removal Of Concrete Formwork

Several factors affect the time of removal of formwork from concrete, here are a few:

The most concrete way (Pun intended.) to estimate whether or not the concrete structure has gained enough strength to strike off the formwork, is to perform tests on concrete cylinders or cubes. The condition is that these cubes or cylinders must be made of the same mix of concrete as the structural member and hardened and cured under the same circumstances as that of the structural member.

How much strength should the concrete have gained before the removal of formwork?

How long do you wait before removing the concrete formwork?

There are several ways depending on various factors to define when the concrete formwork has to be removed.

When Ordinary Portland Cement is used:

Portland Pozzolana Cement (PPC) and Low Heat Cement (LHC) take 10/7th the time Ordinary Portland Cement takes for the stripping of formwork while Rapid Hardening Cement takes 3/7th of that same time.

There are more than one ways to define the correct time for removing the concrete framework. Depending on the material finesse and the structuring the criticality of the process varies.